Purpose
This process takes place in the case of procurement using scheduling agreements.
Process Flow
- Materials Planning generates delivery schedule lines for scheduling agreement items. You can also create schedule lines manually.
- You create scheduling agreement (SA) releases (delivery schedules) comprising the schedule lines for a certain scheduling agreement item. These are snapshots of the overall delivery schedule stored in the system at given points in time. In creating such releases, the system proceeds as follows:
- If a creation profile exists, it aggregates the release (i.e. scheduled) dates and quantities.
- It generates an SA release (forecast or JIT delivery schedule) in accordance with the creation strategy and the entries on the initial screen for SA release creation.
- If a creation profile exists, it determines any backlogs and immediate requirements.
- If a creation profile exists, it checks any applicable tolerances in the case of SA releases created due to changes to the overall schedule in the system.
- The releases (delivery schedules) are transmitted as messages to the vendor.
See also:
Materials Planning and Scheduling Agreement Release
Scheduling Agreement Releases (Forecast or JIT Delivery Schedules)
Creation Profile
Example: Creation Profile/Creating SA Releases.
Messages for Scheduling Agreement Releases