This is how you create a profile in the material master:
1. From the menu screen of the material master record, select Profile
--> MRP profile or Forecast profile --> Create.
The initial Create Profile screen appears.
2. Enter the key you want to assign to the profile.
If you want to use an existing profile as a reference, enter the name of this profile in the Reference field so that the system can copy its values to the new profile.
3. Select Goto
--> Selection screen.
The selection screen appears. It shows all the fields that can be copied to the MRP or forecasting screen of the material master record.
4. Enter a profile description and select the fields you want the profile to contain.
You must also decide whether each field will be copied to the material master record as a fixed value or a default value.
5. Select Goto
--> Data screen.
The data screen appears. Only the fields you marked on the selection screen are presented for you to fill in. The fixed and default values are displayed in different colors.
All fixed values are required fields except where the field can also accept the value BLANK .
6. Enter your data and save the profile with Profile
--> Save.
You now return to the initial screen where you can create another profile.
The data for the MRP profiles are split over two data screens. With Goto Data screen 1 or Data screen 2, you can spring from one data screen to another.
The system runs a number of checks when you create a new profile:
• When you go from the selection screen to the data screen, the system checks whether the selected fields form a reasonable combination and are allowed to appear in the same profile.
The Fixed lot size and Maximum stock level fields may not be combined in one MRP profile.
• When you save the data on the data screen, the system checks
o whether the values you you have entered are valid, for example, whether they are defined in the appropriate table
o whether the values you have entered are compatible with each other
If the Maximum stock level field appears in the profile, you must also specify a Lot size that can give the highest stock level.
If the system detects inconsistencies or errors, it asks you to change the fields selected on the selection screen and/or correct the values.
Wednesday, July 9, 2008
Subscribe to:
Post Comments (Atom)
Archives
-
▼
2008
(141)
-
▼
July
(53)
- Forecast Parameters Topics
- Forecast Parameters Overview
- MRP Forecast Parameters Forecast Models
- Model Selection MRP Forecast Parameters
- Manual Model Selection MRP Forecast Parameters
- Automatic Model Selection MRP Forecast Parameters
- Manual Model Selection with Additional System Chec...
- Model Initialization MRP Forecast Parameters
- Ex-Post Forecast MRP Forecast Parameters
- Parameter Optimization MRP Forecast Parameters
- Maintaining MRP Forecast Parameters
- MRP Forecast Parameters: Independent of the Foreca...
- MRP Forecast Parameters: Dependent on the Forecast...
- Creating Historical Data MRP Forecast Parameters
- Creating Forecast Values MRP Forecast Parameters
- MRP Carrying out the Forecast with Reference to An...
- Maintaining Forecasting Parameters Using Profiles ...
- Maintaining Parameters Using Profiles Overview
- Creating a Profile MRP Forecast Parameters
- MRP Forecast Parameters Displaying a Profile
- MRP Forecast Parameters Changing a Profile
- Deleting a Profile MRP Forecast Parameters
- Carrying Out the MRP Forecast
- Carrying Out the Forecast Overview
- Things to Think About Before Carrying out the MRP ...
- MRP Forecast Options
- Carrying Out the Individual MRP Forecast
- Carrying Out the Total MRP Forecast
- Carrying Out the Total MRP Forecast in Background ...
- Calculating the MRP Forecast Values
- Calculating the Safety Stock and the Reorder Level...
- Ex-Post Forecast MRP Forecast Parameters
- Monitoring the Selected MRP Forecast Model
- How Does the System Optimize the Smoothing Factors...
- MRP Forecast Result Index
- Checking the MRP Forecast Result Using a List
- Checking the MRP Forecast Result in Online Mode
- Changing the Forecast Result
- Significance of the Material MRP Forecast for Mate...
- Material MRP Forecast
- Reducing MRP Forecast Requirements
- Effects on Consumption-Based MRP Planning Procedures
- Splitting the MRP Forecast Requirements
- Forecast Formulae Overview
- Model: Moving Average Forecast Formulae
- Model: Weighted Moving Average Forecast Formulae
- Model: First-Order Exponential Smoothing Forecast ...
- Model: Constant Forecast Formulae
- General Formula for First-Order Exponential Smooth...
- Model: Second-Order Exponential Smoothing Forecast...
- Formula for Evaluating the Forecast
- Formula for Calculating the Safety Stock Forecast ...
- Showing posts with label Forecast Formulae. Show a...
-
▼
July
(53)
No comments:
Post a Comment