To create a planning calendar without a calculation rule, proceed as follows:
The initial screen for maintaining the planning calendar now appears.
The maintenance screen of the planning calendar now appears.
The minimum period is used as a checking limit for maintaining calendars that are no longer valid. By defining the minimum period, you define a period that you can use to process a calendar that is no longer valid. As soon as this checking limit has been exceeded, the calendar is proposed automatically by the system for processing (please refer to Maintaining Calendars that are no Longer Valid). Therefore, you should make sure that the minimum period is long enough so that the planning calendar is proposed on time. You define the validity period of the planning calendar after you have specified the calculation rule.
If you only enter start dates, the finish dates are automatically calculated by the system (except for the last finish date).
If you only enter finish dates, the system will automatically the start dates.